What to include in a VOC treatment inquiry
An air pollution control quotation is only as good as the process data behind it. Two buyers describing “the same” 20,000 m³/h exhaust can need very different equipment, because the deciding variables are not the airflow alone.
| Parameter | Why it changes the answer |
|---|---|
| Exhaust flow rate (Nm³/h or m³/h) | Sets the equipment size and the ductwork; must be stated at normal conditions with the worst case identified |
| Pollutant species and inlet concentration | Determines whether a thermal, catalytic or biological route is viable, and whether the unit can run autothermally |
| Gas temperature and moisture | Drives preheating, condensation risk and the choice of heat exchanger and materials |
| Particulate loading | Particulate blinds catalyst and fouls heat exchange media, so filtration may have to come first |
| Required destruction or removal efficiency | The permit limit, not a generic 99%, defines the design target |
| Presence of halogens, sulphur or silicone | Rules in or out catalytic routes, and sets the material and the quench requirement |
| Operating hours and duty cycle | A unit that stops and starts frequently needs a different thermal design from one that runs continuously |
| Available plot, utilities and power | Often decides between one large unit and two smaller ones |
| Destination market and applicable code | Sets the certification, the electrical standard and the documentation package |
How an inquiry is handled
- Process review — the stream data is checked against the candidate technologies, and any route that cannot work is ruled out early rather than quoted anyway.
- Clarification — missing parameters are requested instead of assumed, because a wrong concentration produces a wrong unit and an unachievable guarantee.
- Technical proposal — the quotation states the design basis, the equipment configuration, the guarantee point and the utility consumption, so it can be compared with another offer on equal terms.
- Documentation — drawings, material certificates and test records are issued with the order.
Frequently asked questions about the inquiry process
Can you quote from an emission limit alone?
Not usefully. The limit sets the target, but the flow rate, the concentration and the pollutant species determine the equipment. Without them any figure would be provisional.
What if we do not have a full gas analysis?
State what is known and what is estimated. A preliminary selection can be made on partial data, but the final guarantee should be based on a measured or design-basis analysis.
Do you work with an existing treatment unit?
Yes. Retrofits, upgrades and replacements are common, and the useful information is the existing unit’s duty, its measured performance and the reason for the change.